What dates are used as start and end for the bars on the Roadmap for classic projects? I'd like to use Target Start and Target End.
Found the answer to this myself. Go to the Plan configuration and you can choose the start and end date fields you'd like to use. https://confluence.atlassian.com/advancedroadmapscloud/configuring-plan-settings-998651354.html
It looks like you're new here. Sign in or register to get started.