I have a screen setup to show when an issue moves from Open to In Progress to allow users to add an assignee since I require it when any item is moved to In Progress.
Is it possible to show the screen only when there's a missing assignee?
Hi @Michael Arndt
There are two options that I can see:
-------------
Condition:
To set this...
Multiple Flows:
If a condition isn't what you're looking for - I have seen teams use a multi-flow approach.
This is what I mean:
That way, only one of the two transitions has a screen. This is a brief overview of how to implement this:
^ A few things to bear in mind:
Let us know if either of these options fit your need!