Please see attached screenshot for easier explanation. We have added a "In Review" stage from the usual classic or next-gen
TO DO
IN PROGRESS
DONE
So it now reads
TO DO
IN PROGRESS
IN REVIEW
DONE
However its messed up our Sprint burndown chart, understandably, as we have our "In review" meeting at the end of the sprint to QA all the tasks moved from "In Review" to "Done".
If the sprint burndown chart tracked when team users changed the status to "In review" we would get a far more accurate result.
is there anyway of doing this please?