First of all I can't get any sales person to call me back from Atlassian re our switch from Aha! to Advanced Roadmaps, for a 1000 person user base.
2nd, when I schedule sprint in my projects they do not show up in my plan. They are in a field that says sprint is external.
How do I create a sprint within the plan so that when I'm doing capacity planning and have my view in Teams and Show Capacity mode I can see my current, or future sprints. If I create a sprint in a project i have no control over it in the plan.
Also the dependency flags are not turning red when lead days are negative, why is that?