I have two projects one named "DARTMX8MP" the second is named "YOCTO" .
I have a task named "DARTMX8MP-7" which depends on the completion of "YOC-7" from YOCTO project.
I set the due date of YOC-7 tor sept. 16th. In the settings or "DARTMX8MP-7" "YOC-7" it is set the it has to be done before "DARTMX8MP-7".
However this is not reflected in BigGantt view .
Tried also "Blocked by" ...
How can this change be reflected in BigGantt view ?
Thanks,