Hello. I do not see the report offering for Epics under my reports tab. Please could someone assist? Thanks!
Hi @Rodger Mann -- Welcome to the Atlassian Community!
To help the community provide input, would you please answer...
Thanks, and best regards,
Bill
Thank you, Bill!
We are using a Classic Project, and a Kanban Board.. I see the following reports:
Hi Rodger,
Thanks for clarifying your set up. The Epic Report is only available for Scrum boards. Perhaps the designers took a very purist view of pull-only, small work items only, Kanban, where this report (and the associated Epic Burn Down) are only relevant for teams using iteration velocity with Scrum.
https://support.atlassian.com/jira-software-cloud/docs/view-and-understand-the-epic-report/
There is probably a marketplace add-on to add a similar report for Kanban.
As a work-around, you could export the epic's issues and create your own report in a spreadsheet. Or, re-purpose one of the dashboard gadgets by assigning your epic and its children to a version.
__Bill
Hi Bill,
Thanks very much for clarifying that! You have saved me a lot of time.
Have a great weekend!
Rodger.