I want to break down a month long major release 1.0.0 to 4 weekly small release 1.1.0>>1.2.0>>1.3.0>>1.0.0. So I want to create a release dashboard which will track all these releases with their weekly due dates. I have a basic JIRA and no advanced plugins. what's the most effective way of doing these, few alternatives are appreciated.
Currently we do a monthly release with a fix version and we are following a scrum ban approach not a typical scrum where we are tracking completion of items as per Due date of the major release and there is no mention of data in the due date field of the individual issues.
Say release due date in release tab is 30.07.2020
so all items/issues are tracked with this date but there is nothing mentioned as a due date for individual issues in JIRA.
Please suggest