Hello good afternoon;
I have a question, in big picture, in the Roadmap module, where I can edit the dates shown in the PI section, image is attached.
Hello,Program Increments and Iterations are managed (creating and editing) from the Overview module. If you want to edit PI or Iteration start & end dates, please go to the Overview module (hierarchy view), then find a given Iteration and click “Edit” as on my screenshot below (BP 7.11.16).
More information regarding the Agile Schedule you can find in the article: Adding new boxes.
Cheers,Anna
Hi Anna;Thank you very much, the information was very useful
Regards
You are welcome! Please let me know if you have further questions.
Cheers