I created a subtask called "Bug-SubTask" so that i can capture insprint bugs and get them solved in the sprint also for quick creation of bugs in a sprint with traceability. However, i cant get this subtask to impact the % contribution to the story as it does affect the storys readiness and % complete of the story. My thought was by adding any type of subtask it would automatically contribute to the % completeness of the story.
A regular subtask in a JIRA story contributes to the % complete in a story. My bug subtask should impact the story likewise is my thought. I may later have to drive calculation off the story point also of the bug-subtask, but i'll figure that another day.
-- One observation is if my story had no subtasks and only (1) bug subtask it wont even show the bug-subtask part of percentage complete. However, If my bug subtask exists with other regular subtasks and /or other bug-subtasks, it DOES show the percentage complete. Ex: 3 task(done) 5 bug(TODO) subtask, it will show 37% complete.
2 bug-subtasks (2 TODO) 100% incomplete.
This narrows down that 1 subtask alone will not show the % completeness view.