Trying to setup an automation that when a sprint is started the Start Date field sets to the date the sprint is started change the start date to today (current sprint start date) and make the end date for all issues in the sprint 10 business days out but i keep getting errors
Hi @Clark Everson
Looking at your rules, the actions are listed after the branch, not inside it. Note the plus sign to add a component to the branch under its tree. Try to re-add your components (the edits) and then delete the ones after the branch.
Best regards,
Bill
Hi @Bill Sheboy ,
So I got rid of the errors, but the dates aren't setting. Unsure why.
Regards,
Clark
images didnt attach
Thanks for the updated images.
Your rules say to only update the Start Date when it wasn't empty. Same for Due Date.
Is that what you want to do: only replace the dates, not set them when empty?
I don't know