There is 3 status under the roadmap view -
todo
inprogress
done
however I can’t map my done epic to the done status used in this view ?? What am I missing ?
thanks
Hello Uma,
Thank you for reaching out to Atlassian Community!
Just for a better understanding of the issue, I would like to know if it's possible to share with us a screenshot of where you need to change the Epic status.
On next-gen projects, there are three types of statuses To Do (Gray), In Progress (Blue), and Done (Green). So, even if we change the name of those statuses on the board or adding more Blue statuses, it will always show those three names on the Roadmap because it's related to the type and not the status itself.
When filtering the tickets by status, it will also show open Epics that contain closed child issues, and to change the status of an Epic it will be necessary to click on it to open on the right side.
Please, let us know more details about your use case, so we can test here to check what is happening.
Regards,Angélica
Hi Angelica
i got this working however i want to be able to show at the roadmap level where an EPIC / EPICS are blocked with a dot or with a symbol ? is this possible ..
Uma
It's possible to add "Blocks" between Epics using the dependencies on the Roadmap.
For more information about dependencies and all other features for Epics, please check the documentation below:
Thanks for the reply .. i understand with dependency it can be shown .. however activities such as decision making and top management approval can’t EPiC - it’s key task that holds things up
was wondering if I could highlight a colour or feature to show the status Of the epic “blocked” at the epic level view at all ?