Our team is utilizing Jira Cloud - and we have a straight forward process of Estimating all of our work and setting it to "To Do" to grab as we go. I want to be able to automate the Due Date field so that when our devs transition the issue to "In Progress", and if the due date is empty, set the Due Date to when it's transitioned (now) to (now + Original Estimate).
The automation rule in Jira is easy for setting up the conditions, but the action for adding the Original estimate is where I'm blocked.
From this documentation: https://support.atlassian.com/jira-software-cloud/docs/smart-values-date-and-time-functions/ I can only find syntax for {{now.plus[insertknownquantity]}}
How do I get that [insertknownquantity] to not be a fixed time, but instead pull from the Original Estimate field?