Hello,
We have a seen on a disconnect between time that is logged on subtasks and what is shown in the time tracking module.
When logging time on subtasks, it is not rolling up to the parent ticket.
Here is an example of a parent ticket
It has a rough size of 3 days and an original estimate of 3 days.
![2020-05-26 15_58_07-[QAUTO-4384] Transition Suites to 2020.2.0 and run them - JIRA and 11 more pages.jpg 2020-05-26 15_58_07-[QAUTO-4384] Transition Suites to 2020.2.0 and run them - JIRA and 11 more pages.jpg](https://us.v-cdn.net/6038660/uploads/images/96518i7F4D07D185549EFB/2020-05-26%2015_58_07-%5BQAUTO-4384%5D%20Transition%20Suites%20to%202020.2.0%20and%20run%20them%20-%20JIRA%20and%2011%20more%20pages.jpg)
Here is the time tracking module for that same parent ticket.
![2020-05-26 15_59_02-[QAUTO-4384] Transition Suites to 2020.2.0 and run them - JIRA and 11 more pages.jpg 2020-05-26 15_59_02-[QAUTO-4384] Transition Suites to 2020.2.0 and run them - JIRA and 11 more pages.jpg](https://us.v-cdn.net/6038660/uploads/images/96519i6478BBA2AD886690/2020-05-26%2015_59_02-%5BQAUTO-4384%5D%20Transition%20Suites%20to%202020.2.0%20and%20run%20them%20-%20JIRA%20and%2011%20more%20pages.jpg)
6 hours of work were logged on subtasks (which do not have original estimates on them). I would expect that the time logged should subtract from the time remaining.