The percent complete calculation for a Jira epic appears to use issue count rather than story point size. Is there a way to calculate based on story point size?
As an example:
If an epic has 3 stories of size 0.5 points, 3 points, and 5 points. The first story (0.5 point) is complete and the two other stories (3 and 5 points) are incomplete.
The epic percent complete calculation says the epic is 33% complete (1 story/3 total stories) but I want it to calculate percent complete to be 5.8% (0.5/8.5).