Unable to complete a sprint - getting the message:
Sprint cannot be completed as there are incomplete subtasks on the following issues
Understand that incomplete subtasks would prevent me from completing the sprint.
I have the administrative permission and created a customized column "Cancelled" in the board in which the incomplete subtasks belong.
Would it be possible to configure the sprint to complete both the Done and Cancelled issues/tasks/subtask?
Temporarily i have moved the entire parent issue to the next sprint.