How can I get consolidated report for total number of story points assigned vs total number of story points completed for a particular sprint for every particular team member right before the sprint is closed
Hello @vinit_kumar
Thank you for reaching out.
I believe the velocity report might provide you all the story points committed and completed in your Sprints at any time you want:
- View and understand the velocity chart
Basically, the Velocity Chart shows the amount of value delivered in each sprint, enabling you to predict the amount of work the team can get done in future sprints. It is useful during your sprint planning meetings, to help you decide how much work you can feasibly commit to:
Please, take a look at the documentation provided and let us know if this is the report you need.
@vinit_kumar You can use sprint health gadget. This will give you the progress of sprint