The team is thinking of having a hardening sprint of 1 week after every 3 sprints (each sprint of 2 weeks). So, basically a release would comprise of such milestones (3 Sprints + 1 Hardening Sprint).
This way, the team will get sufficient time to have regression testing, code clean-up etc. after every 3 sprints and we can avoid backlog getting piling up.
Is this a standard idea across industry?
I am also concerned about the velocity chart. The hardening sprint activities won't have any story points. If at all we use story points for these tasks, then also the duration of hardening sprint is of only 1 week.
So, should only the Jira Board query (to exclude these hardening sprints) sufficient to have a correct velocity chart?
Any other suggestion?