I recently added a workflow status with transitions to my teams project. The status is called "In Review" and the transitions that are in the workflow regarding this are:
- "In Progress" to "Code Complete" (Pull Request created)
- "Code Complete" to "In Review" (A Code Reviewer is looking at the Pull Request)
- Pull Request declined: "In Review" to "In Progress"
- Pull Request accepted: "In Review" to "Complete"
Now whenever a Code Reviewer changes the status of an issue to "In Review" for some reason it removes the issue from our Current Sprint. Then once the Code Reviewer accepts/rejects the Pull Request and it transitions to one of the pre-existing statuses, the issue is added back into the Current Sprint.
This is showing as "Scope Change" and looks really bad for our reports. Any help is appreciated!