How do I calculate time spent on the parent tasks(I'm referring to the stories)? Time spent is there in sub-tasks level but it doesn't sum up to the stories level.
Thanks!!
Hi @Ratna Bikram Adhikari ,
It is an open bug with Atlassian. Please refer
https://jira.atlassian.com/browse/JRACLOUD-69587?_ga=2.6138291.1006777655.1577320135-1123603557.1577320135
Workaround is Turn off the New JIRA Issue View.
https://community.atlassian.com/t5/Jira-Service-Desk-questions/Missing-the-checkbox-quot-Include-sub-tasks-quot-in-Time/qaq-p/772359