Stories are estimated using story points whereas Tasks (and not sub-task) are estimated using time unit.
Velocity chart only shows story points. If I want entire effort to be reflected in velocity report, then Story and Task both should be estimated in the same unit i.e. story point.
My question is how can I achieve that?
Can I add a custom field for story point for Task?
If I can, then will its points be considered in velocity report?