I need to know if any of the reports that JIRA provides will be incorrect if we are using JIRA this way:
Story Point field: data we are entering is .25,.50.1,2,3,4,5,6..... In the eyes of the team this is considered days.
Log Time: pretty normal 30m, 1d, 4d,..... Users are logging time upon closing a story.
Example: Story 1 is created with a story point of 4, the time logged upon closure is 3d.
Subtasks are optional if the story is only being done by one person.
We are not using the 'Original Estimate' or 'Remaining Estimate' fields.
If we are not using JIRA the way it was created which my understanding is:
- Story Point = effort
- Every Story should have a subtask with the 'Original Estimate' date input.
- Team should log time daily (so we can obtain the velocity)
Our backlog is filled with stories with the story point field data entered, no original estimate.
Are we hurting our ability to obtain the metrics JIRA provides by not using the Original Estimated field and not creating subtasks?