I'm using a JQL to import my Jira issues to MSP using Ceptah Bridge.
My code is set up to ask for the Initiatives, with linked Epics, and stories/dev tasks that are related to each Epic.
issue in linkedIssues(TIPSN-6) OR ("Epic Link" = TIPSNRCRM-666)
I've then added a line to exclude any issues with the status's we deem as complete
AND status != "Code Complete"
However, when I combine my JQL filter for all our current work it is still pulling over the Epics that have a completed status.
Is there a way using the JQL to apply the status exclusions to the Epic Links?
Or is it ignoring the exclusions because I've called the Epic links specifically.