Hello,
We had a sprint in progress and an issue in the backlog was noticed and fixed. The issue was added to the sprint and shows up in the burn up report but the date and log for the burn up report is wrong, it seems to show as the "Created" date rather than the date the change was made.
for example, the issue was created on Oct 24th at 3:53pm but was added to sprint on Oct 29th at 8:00am. Burn up report reads as added on Oct 24th.