HI
Once an issue on the kanban board is in final status - I would like to see it on the finished items column for a period of time and then to have it removed otherwise the column is getting packed.
How do I do that?
Thanks,
Hi RonyYou need to use Kanban board sub-filter. For example:
resolved >= -1w
https://confluence.atlassian.com/jirasoftwarecloud/configuring-filters-764477988.html
Hi @Rony Len what we are doing is indeed like Maksim suggested which is
YOUR FILTER AND (status != closed OR status changed to closed after -7d )
In Jira Server, there is a built-in option to do this, without even changing the filter.
How do I use the argument "status change to" with several statuses?
to confirm - when using "after -7d" means the last 7 days?
My target is to have it effecting only the column that represents certain statuses that are equivalent to final status
@Rony Len
It seems to me the most correct decision will be based on a resolved date:
But at the same time, nothing prevents to list all the final statuses:
status changed to closed after -7d OR status changed to Cancelled after -7d