It's bit confusing...if i enter 50hrs..it should show 50 hrs...rather can week and days...I tried in global settings too....but not getting reflected...can u please suggest a solution
Hi @Deepan V.R
You could try changing the default unit for time tracking as described here.
https://confluence.atlassian.com/adminjiracloud/configuring-time-tracking-818578858.html
Regards
Tom
Go to admin -> configure time tracking, and change the display from "pretty" to "hours". This is a global change, affecting all estimates, and warn your users first, as they may be confused by it
Jira settings > Issues > Time tracking ... click Edit global settings and change your Time display format.
It's fine in the story's grey bubble...But in the original estimate and remaining estimate again it estimates in days...