Time Tracking is currently ON. The number of working hours per day is 9. The number of working days per week is 5.
*************************************
Hmm lets see, from my count:
1 - March 26th2 - March 27th3 - March 28th4 - MArch 29th5 - April 2nd (March 30th is a non working day)6 - April 3rd7 - April 4th8 - April 5th9 - April 9th (Release date, April 6th is a non working day)
Sums to 9 days, The bigger question is how did you get 13
I'm not sure that my logic matches what Jira is doing, but I get 9 days too
Your sprint is set to cover three weeks, as below. My x's represent the days you've said "non working day", and the numbers are a counter.
20 Mar Tue 1 21 Mar Wed 2 22 Mar Thu 3 23 Mar Fri non-working 24 Mar Sat non-working 25 Mar Sun 4 26 Mar Mon 5 27 Mar Tue 6 28 Mar Wed 7 29 Mar Thu 8 30 Mar Fri non-working 31 Mar Sat non-working 1 Apr Sun 9 2 Apr Mon 10
3 Apr Tue 11 4 Apr Wed 12 5 Apr Thu 13 6 Apr Fri non-working 7 Apr Sat non-working 8 Apr Sun 14 9 Apr Mon 15 Release
By my counting, you should therefore get 15 days.
However, your time-tracking says there are only 5 working days per week, so you need to remove 2 days per working week, which means you get 15 -6 = 9 days...
Thanks for your reply but
20 [1], 21[2], 22 [3], 25 [4], 26 [5], 27 [6], 28 [7], 29 [8], 1 [9], 2 [10], 3 [11], 4 [12], 5 [13], 8 [14], 9 [15]
20 [15], 21[14], 22 [13], 25 [12], 26 [11], 27 [10], 28 [9], 29 [8], 1 [7], 2 [6], 3 [5], 4 [4], 5 [3], 8 [2], 9 [1]
Although non wroking days calculated before 6 days
Today 26 / 3 / 2012 >>>> The counter on dashboard now {8} , the counter must be 26 [11] 11 Days
If you have answer for this issue please reply me
I'm sorry, my formatting got all messed up when I posted the original. I've re-done it as a code block, which seems more clear.
I don't understand what you're asking now though. What I'm trying to point out is that you have told Jira that your sprint is 21 days long, with 6 non-working days, and 5 working days per week (i.e. 2 in 7 are also non-working). 21 - 6 - (3 * 2) = 9 days. Whatever order you do the two "2 days not working", you get 9 working days in the three weeks.
Our Sprint is 15 days without non working days