There is a conflict between one team's velocity chart and the story points shown in the Sprint Report. I can't figure why. Here is some context:
- Jira Cloud
- Classic project, not next-gen (for all projects)
- Checked velocity reports from other projects, none show inconsistencies in story points (or anything else)
- I think all board & project settings are the same across boards, but... I haven't checked. Could that even have an effect?
- new team, first sprint
- Velocity Chart shows 33 committed and 23 completed.
- Sprint Report shows 28 committed and 18 completed
- The difference b/t committed & completed is 10 for both reports
- FWIW, the Sprint Report is correct and the Velocity Chart is wrong.
Screen shots of each report:


Any ideas on what is going on here?
Thanks, in advance, for your help.