So we have two different boards one for dev and one for ops. The dev one runs over a period of 4 weeks ops 1 week as usual i finished the ops sprint carried over to the new one but it wont let me start the new ops sprint until the dev one is closed. I dont get why they are two different boards with seperate tickets can anyone help?
@joe cromie , May be you will have to enable Parallel sprints? https://confluence.atlassian.com/jirasoftwareserver0713/using-parallel-sprints-965542557.html