Hi Jira gurus,
I need your help with making Jira to include bug estimates in velocity reports.
We are using Jira cloud. I've added Story Point Estimate field to the Scrum Bug screen. When I create bugs I can see and enter the estimation field. But the estimation is not counted in the velocity or current sprint size reports.
There are many bugs that get assigned to the sprint during sprint planning. Without bug estimations included in reports, it looks like the team delivers less work at the end of sprint. For example, let's say our velocity is 72 points. We take on user stories worth of 50 points, and 5 bugs each estimated at 4 points. You'd think the sprint size would say 70, but it doesn't - it says 50.
How could I fix it?