How can change the view of dependencies to a particular issue in "Plan" view?

Hitarth Bhalla February 13, 2025

Hi,

In Plan view while visualizing timeline of a project the dependencies are viewed in a card format. can we change this view.

 

I need the dependencies in a column structure below the ticket.

1 answer

0 votes
Pasam Venkateshwarrao
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
February 17, 2025

Hi @Hitarth Bhalla 

 

Dependencies, also called Issue Links in other parts of Jira, allow you to show the order in which issues need to be done. If there’s a dependency between two issues, one must be finished before the next can begin.

In order to use this feature, a Jira admin needs to enable issue linking. The timeline can only show issues with the Blocks issue link type and link issues from a single project. Learn how to enable issue linking.

 

To show or hide dependencies on your timeline:

  1. From your timeline, navigate to the View settings menu at the top-right of your view.

  2. Under the More details heading, tick the Dependencies box.

source link: https://support.atlassian.com/jira-software-cloud/docs/show-or-hide-dependencies-on-your-roadmap/

 