Hi,
In Plan view while visualizing timeline of a project the dependencies are viewed in a card format. can we change this view.
I need the dependencies in a column structure below the ticket.
Dependencies, also called Issue Links in other parts of Jira, allow you to show the order in which issues need to be done. If there’s a dependency between two issues, one must be finished before the next can begin.
In order to use this feature, a Jira admin needs to enable issue linking. The timeline can only show issues with the Blocks issue link type and link issues from a single project. Learn how to enable issue linking.
To show or hide dependencies on your timeline:
From your timeline, navigate to the View settings menu at the top-right of your view.
Under the More details heading, tick the Dependencies box.
source link: https://support.atlassian.com/jira-software-cloud/docs/show-or-hide-dependencies-on-your-roadmap/