Is it possible to create 'Action Plans' where the first task has a set date and then the next is always 3 days followed by the third task 2 days after etc.
We have projects that require several different members throughout it and need something to help them stay on the same page and run efficiently.
Yes this can be done with automation and works well but it is very convoluted.
It is worth looking at the planning power-ups like Planyway to get similar capability