This, like many Jira articles, is missing some steps. How do I get to the graphical scheduler in the first place? This tells me how to configure it, but I can't even find it to get started! Please advise.

This question is in reference to Atlassian Documentation: Using the graphical schedule

This, like many Jira articles, is missing some steps.  How do I get to the graphical scheduler in the first place?  This tells me how to configure it, but I can't even find it to get started!  Please advise.

1 answer

Hi PJ!

Try this:

  1. From your JIRA dashboard, click on the Portfolio button at the top of the screen.
  2. Click All Plans.
  3. From there, either choose the plan you're after, or click the New Plan button in the upper right.
  4. Once on your plan screen, note at the very bottom there's the schedule, (see  screenshot). 
  5. From there, you can click on the '...' and drag it up to reveal all the buttons mentioned in the documentation.

Let me know if you run into any issues!

Thanks!

 

Suggest an answer

Log in or Sign up to answer
Community showcase

Scrum Roles Explained: the Do's and the Don'ts

Hello Community,  Today we are going to talk about the three Scrum Roles. There is the Development Team, the Scrum Master and the Product Owner. In my opinion these three are all really impo...

144 views 2 6
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you