How to end a sprint?

Hello,

I am following this steps to end a sprint.

http://confluence.atlassian.com/display/GH/Ending+a+Sprint

However, I get message, "Sprint cannot be completed as there are incomplete subtasks on the following issues: XXX" even though all subtasks are done.

My team is using our own workflow (not JIRA default) for technical subtasks, and it is all marked as "Done" (please refer screenshot).

Why I cannot end sprint? What am I missing here?

Thank you!

Miki

1 answer

1 accepted

Make sure in your custom workflow, the transition to your Done status actually resolves the issue. This is usually handled by setting up a post function for the transition that fires an Issue Resolved event. See workflow documentation for more detail: http://confluence.atlassian.com/display/JIRA/Configuring+Workflow#ConfiguringWorkflow-workflowresolutions

Hi Danielle,

Thank you for your answer!! I knew I was missing something in my custom workflow, but I could not figure. I was able to end a sprint properly.

Miki

Miki, you are most welcome. Glad it helped.

Suggest an answer

Log in or Sign up to answer
How to earn badges on the Atlassian Community

How to earn badges on the Atlassian Community

Badges are a great way to show off community activity, whether you’re a newbie or a Champion.

Learn more
Community showcase
Posted Tuesday in Uncategorized

Friday fun: how many celebrates Midsummer holiday or is this a Swedish tradition only?

Any other country that celebrates Midsummer holiday (this friday 22 June)?  

42 views 3 1
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you