How to end a sprint?


I am following this steps to end a sprint.

However, I get message, "Sprint cannot be completed as there are incomplete subtasks on the following issues: XXX" even though all subtasks are done.

My team is using our own workflow (not JIRA default) for technical subtasks, and it is all marked as "Done" (please refer screenshot).

Why I cannot end sprint? What am I missing here?

Thank you!


1 answer

1 accepted

Make sure in your custom workflow, the transition to your Done status actually resolves the issue. This is usually handled by setting up a post function for the transition that fires an Issue Resolved event. See workflow documentation for more detail:

Hi Danielle,

Thank you for your answer!! I knew I was missing something in my custom workflow, but I could not figure. I was able to end a sprint properly.


Miki, you are most welcome. Glad it helped.

Suggest an answer

Log in or Join to answer
Community showcase
Louis De Jaeger
Posted Thursday in Off-topic

Friday fun: your best joke

Hi all Lets make this Friday fun really fun and post one (or more) of your best jokes! The joke can be about an Atlassian product, or just a really fun joke you want to share! I’m not the best j...

190 views 12 3
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you
Atlassian Team Tour

Join us on the Team Tour

We're bringing product updates and pro tips on teamwork to ten cities around the world.

Save your spot