A product manager is responsible for both the APP and web requirements, but APP and web are different R&D teams. I need to plan versions of APP and web respectively, so I want a task to appear in both the web sprint and the APP sprint.
Hello,
It is not possible to see a task in two active sprints. It is possible to see it in multiple closed sprints and one active sprint.