Effective way of Resource utilization on portfolio Edited

I am trying to use Portfolio to plan our development timelines and ensuring effective resource utilization. However, facing issue as resource utilization is not as per our expection.

We are developing mobile apps (iOS, Android) with app Backend (web services). The estimates for each tasks are already entered in Portfolio.

Screen Shot 2017-08-17 at 8.27.16 AM.png

In above example "Wishlist" is user story, with sub-tasks for each of iOS, Android and Backend. The estimate for iOS and Android tasks is 7 days, however estimate for Backend is 2 days.

Now as per my understanding, the Backend guy should start on next user story "Saving Payment Cards", after 2 days, and iOS/Android guys should keep on working on "Wishlist". But according to portfolio, the backend guy will start working on next feature after 7 days (when iOS/Android are also finished). Which is actually not correct, as he would have already finished his work in 2 days and will be sitting idle. 

Is there any why to effectively use portflio in such scenerio?

2 answers

0 vote

Hi @Khawar Shahzad,

I would need more details than what I can see from the screenshot to know exactly what's going on, but it seems that there is a mix up between stages and skills. 

Stages work in sequence, whereas skills work in parallel. You currently have one stage defined (which seems superfluous) and I can't which skills are defined. 

This page explains how stages and skills work:

Perhaps it can help you. 

Cheers,
Allard

Hi @Allard van Helbergen

Thank you for reply. Here is more information:

There is 1 stage "Development", with 3 skills (iOS, Android, Backend)

Screen Shot 2017-08-19 at 12.10.45 PM.pngThis how the team is created.

 

Screen Shot 2017-08-19 at 11.23.38 AM.png

This is the schedule with estimate for all iOS, Android and backend.

 

Screen Shot 2017-08-19 at 12.13.08 PM.png

As you can see, estimate for "Wishlist -  iOS" and "Wishlist - Android" is 7 days. However, the estimate for "Wishlist - BE" is 2 days. 

What I want is that, backend developer should start on next task "Saving Payment Cards - BE", after 2 days, not 7 days. But according to portfolio, backend developer will start next task after 7 days (when iOS and Android is also finished with their task).

Hi @Allard van Helbergen

Could you please help, as per information I provided? If I have one stage, then all the 3 skills should be parallel in this stage.

As per my observation it is already parallel, but resources are not moving to next feature, until all resources complete that a feature.

One more thing I noticed is that even though we are allowed to place estimations on subtasks in Porfolio and the amount sums up correctly on a Story level the value does not refresh the state in Jira after committing the change. When I look at my ticket Estimate and remaining are still blank and all my Jira reports do not work correctly since  I don't have a value in the Estimated field.

 

How to resolve that issue?

Suggest an answer

Log in or Sign up to answer
How to earn badges on the Atlassian Community

How to earn badges on the Atlassian Community

Badges are a great way to show off community activity, whether you’re a newbie or a Champion.

Learn more
Community showcase
Posted Jun 26, 2018 in Portfolio for Jira

New Portfolio for Jira Getting Started Guide

We've just launched a brand new guide to help you get started with Portfolio for Jira.  This guide is a companion piece to our new demo. The guide walks you through use-cases, best practices an...

246 views 7 4
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you