Time in Status custom field for Jira Data center

Naman Jain August 16, 2023

Hi Everyone

I am looking for ways to get time spent in specific status within Jira software data center basicly looking for the report which show time spent in status for single issue type

3 answers

1 vote
Emre Toptancı _OBSS_
Marketplace Partner
Marketplace Partners provide apps and integrations available on the Atlassian Marketplace that extend the power of Atlassian products.
August 16, 2023

Hello @Naman Jain

Jira doesn't give this as a ready-to-use report. But all the raw data needed to calculate such a report is available in each issue's history.

I suggest you use a marketplace app to get ready-to-use reports on this.

Our team at OBSS built Time in Status exactly for this. It is available for Jira Server, Cloud, and Data Center.  

Time in Status mainly allows you to see how much time each issue spent on each status or each assignee

tisCloud_StatusDuration_LeadTime_with Estimates.png    tisCloud_AssigneeDuration.png

You can combine the time for multiple statuses to get metrics like Issue Age, Cycle Time, Lead Time, Resolution Time etc. 

For all numeric report types, you can calculate averages and sums of those durations grouped by the issue fields you select. For example total in-progress time per customer or average resolution time per sprint, week, month, issuetype, request type, etc. The ability to group by parts of dates (year, month, week, day, hour) or sprints is particularly useful here since it allows you to compare different time periods or see the trend. 

tisCloud_StatusDuration_LeadTime_Average_TimeGrouped.png

The app calculates its reports using already existing Jira issue histories so when you install the app, you don't need to add anything to your issue workflows and you can get reports on your past issues as well. It supports both Company Managed and Team Managed projects for Jira Cloud.

Time in Status reports can be accessed through its own reporting page, dashboard gadgets, and issue view screen tabs. All these options can provide both calculated data tables and charts.

Gadget_AverageStatusDurationByComponent.png  tisCloud_StatusDuration_LeadTime_Chart.png tisCloud_IssueView_Data.png

https://marketplace.atlassian.com/apps/1211756/

EmreT

0 votes
RVS_Support
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
August 16, 2023

Hi @Naman Jain 

If you are open for a mktplace solution, you can try out our add-on

Time in Status Reports 

The app provided multiple reports to get:

- time in status for Jira issues

- how long colleagues have been assigned to issues

- average time issue has been spent in each state

- date of issue entry into a status

- transition and status count for each issue

- Group your statuses to define your own Cycle/Lead times

Disclaimer : I work for RVS, the vendor for this app

TIS.PNG

0 votes
Mehmet A _Bloompeak_
Marketplace Partner
Marketplace Partners provide apps and integrations available on the Atlassian Marketplace that extend the power of Atlassian products.
August 16, 2023

Hi @Naman Jain

You can try Status Time Reports app developed by our team. It mainly provides reports and gadgets based on how much time passed in each status.

Here is the online demo link, you can see it in action and try without installing the app. For your case, you can have a look at Time in Status for Each Issue report. For further details, please check Status Time Reports How to Videos.

  • This app has a dynamic status grouping feature so that you can generate various valuable reports as time in status, time in assignee, status entry dates and status counts, cycle time and lead time, average/sum reports by any field(e.g. average in progress time by project, average cycle time by issue creation month).
  • You can search issues by Project, Issue Type, Status, Assignee, Issue Creation/Resolution Date(and any other Date field) and JQL Query.
  • Status durations are calculated according to the working calendar you define. Once you enter your working calendar into the app, it takes your working schedule into account too. That is, "In Progress" time of an issue opened on Friday at 5 PM and closed on Monday at 9 AM, will be a few hours rather than 3 days.
  • You can set different duration formats.
  • You can export reports in CSV file format and open them in MS Excel.
  • You can also add this app as a gadget to your Jira dashboards and reach “Status Time” from Issue Detail page.
  • You can enable/disable access to Status Time reports&gadgets and Issue Detail page per project, users, groups or project role.

If you are looking for a completely free solution, you can try the limited version Status Time Free.

Hope it helps.