Hi
I've got a question from one of our project managers he has noticed that there some differences between Version workload report and Agile time etimate even tough it's the same milestone that is being measured.
ex Version Workload Report says 3180 hours while Agile says 6132 hours have anyone else noticed any diferences in their projects.
I think it is a question of interpretation. It is not good to have two definitions of what is remaining, but in a way they are both right.
My own solution is to set the remaining estimate to 0 when resolving issues (They are done, right?). Unfortunatly I found other differences that I could not explain.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I am seeing a similar problem - we have time remaining against issues in a "Reviewing" state, i.e. not "Done" - but this is not being added into the Total Time Remaining in the Version Workload Report .
I think its a straightforward bug - The Time Tracking report shows 21d 6h 25m remaining, the version workload report only 20.5d.
Greenhopper shows the correct remaining time.
We have JIRA v5.1.5.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Eirik
thanks for the promt answer, do you if this is a bug or that we need any other settings so we can prevent those diffencies?