Tempo Planner Time Missing

Chris S May 27, 2014

Is there a way in Tempo Planner to look at a given week and see how much time a person has recorded? I thought this was part of the Temp Core product but can't find it.

Thanks,
Chris

4 answers

1 accepted

0 votes
Answer accepted
Susanne Götz [Tempo]
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
May 29, 2014

In the Capacity report, you can see time that had been planned for users by using the time navigation. Acutal hours worked are only visible in Timesheets after a users has logged his work, they are not visible in Planner.

1 vote
Susanne Götz [Tempo]
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
May 29, 2014

In the Capacity report, you can see time that had been planned for users by using the time navigation. Acutal hours worked are only visible in Timesheets after a users has logged his work, they are not visible in Planner.

0 votes
Chris S June 10, 2014

Thansk Susanne, much apprecaited!

0 votes
Susanne Götz [Tempo]
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
May 27, 2014

Hi Chris,

When planning time in Tempo Planner, you can view the hours planned for a Team member in the Capacity report. To access this report, go the the Team -> Reports, Team Capacity. In this report you can view the %planned on a member and the available (unplanned) hours for different timeperiods (daily, weekly, monthly and quarterly).

If you are also using Tempo Timesheets (7.9. or later), hours planned on Issues, Versions and Components will show in the Timesheets, as Tempo Core is used by both plugins.

Kind regards,

Susanne

Chris S May 29, 2014

Susanne,

This does work prefectly for looking at how many hours are planned for someone. However, what aboutt ime for last week. Are there any reports that show past time that has been completed or is that only available for Tempo Timesheets?

Thanks,
Chris