Create
cancel
Showing results for 
Search instead for 
Did you mean: 
Sign up Log in
Celebration

Earn badges and make progress

You're on your way to the next level! Join the Kudos program to earn points and save your progress.

Deleted user Avatar
Deleted user

Level 1: Seed

25 / 150 points

Next: Root

Avatar

1 badge earned

Collect

Participate in fun challenges

Challenges come and go, but your rewards stay with you. Do more to earn more!

Challenges
Coins

Gift kudos to your peers

What goes around comes around! Share the love by gifting kudos to your peers.

Recognition
Ribbon

Rise up in the ranks

Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!

Leaderboard

Come for the products,
stay for the community

The Atlassian Community can help you and your team get more value out of Atlassian products and practices.

Atlassian Community about banner
4,639,444
Community Members
 
Community Events
196
Community Groups

Sprint scope not showing in Big Picture (8.6.4)

Edited

We are having an issue displaying the scope of a Sprint in Big Picture. However, it works in our Pre-Prod environment for the same project with the same configuration and data. Our Production system works for other projects. We have synchronised every setting we can find between Prod and Pre-Prod and have even upgrade to 8.6.4, but with no joy. It seems to be only one project and only in Production that it doesn't find the scope, or at least the system tries to display it and then reports that nothing is present in the sprint!

We have setup a hierarchy of Boxes. So the top level scope shows, but the Hybrid Stage, and the iteration do not show.

Please help!

1 answer

Issue resolved. The Project in question were working from a corrupt sprint. We created a new sprint and realigned the issues, and everything works perfectly.