Can structure.gantt calculate start date using manually set finish date and the original esrimate?

Surekha Gupta May 12, 2023

I have configured my Gantt for structure to use manual scheduling and my Finish date is based on a formula that uses custom field. I want the Gantt to calculate the start date using the finish date and the "Original Estimate".

My task bars correctly pick may custom field to use as the finish date, but the start date is not calculated on the basis of formula I entered (Gantt Finish date - original Estimate).

I have two other issues: a) I was able to use a variable called OriginalEstimate and set it to Original Estimate in the formula for start date but cannot find it in standard attributes when I try to use it to set fixed duration based in that section b) I don't know if need to use work estimates section preceding the manual scheduling at all.

I thought I will post some snapshots of my configs. Here is issue configuration.

image.png H

 

Here is my Gantt scheduling configuration

image.png

And finally, here is how it appears on the gantt chart

image.png

2 answers

1 accepted

2 votes
Answer accepted
David Niro
Marketplace Partner
Marketplace Partners provide apps and integrations available on the Atlassian Marketplace that extend the power of Atlassian products.
May 17, 2023

Hello @Surekha Gupta ,

For the formula, you will want to use the JIRADAYS function to convert the original estimate into strictly days and then use the DATE_SUBTRACT function to count back from your end date the number of days returned.

Something like this:

DATE_SUBTRACT(codecompletetargetdate,JIRADAYS(OriginalEstimate),"day")

For problem a) this is due to how that particular field is formatted.  You can try using the formula below.  That being said, your duration is going to come from your end date and formula above, so you probably just want to leave it set to "Store in Gantt chart"

JIRADAYS(OriginalEstimate)

For problem b) if you're always going to have the Finish Date and Original Estimate populated for each issue, you probably do not need to use Work Estimates.  You can leave them as is and know that if you see them being used it is most likely because one of the fields I mentioned is not populated.

Hope this helps!

Best,
David

Surekha Gupta June 8, 2023

Thanks David, after setting start date using the formula you provided, my start date gets set correctly now.

Like # people like this
Surekha Gupta June 21, 2023

Hi David, I was trying to do resource levelling and realized that when I use the formula '

DATE_SUBTRACT(codecompletetargetdate,JIRADAYS(OriginalEstimate),"day") 

Then I am counting calendar days instead of working days. How can I set my start date to be "Original Estimate" worth of working days before the end date?

0 votes
Surekha Gupta May 12, 2023

sorry, instead of editing my post I added information as answer, ignore. I am still hoping someone can help me figure how to draw "ETA based scheduling chart."