Logging Time - Rolling up to the Epic

Hello, 

 

When my team logs time at the subtask level that information is rolled up to the story. How come the totals at the story level are not rolled up to the parent epic? The estimated and remaining values from the child stories exist on the epic and appear to update but not the logged time. 

 

What is the reasoning behind this? Is this something on the roadmap to change?

2 answers

following as I am interested in the answer to this too.

Out of box JIRA cannot provide you this information.

However as a workaround try this.

  • use search to search for the issues underneath the epic.

epiclink=<name of epic>

  • add Sigma time logged and sigma remaining time to the columns
  • Extract theinformation into an excel
  • Use excel features to sumup the total of time logged  and remaining estimate.

Rahul

 

This seems like a fairly shocking omission, very much a basic project management tool. Do you have an ETA to resolve this issue? Thanks.

Suggest an answer

Log in or Sign up to answer
Community showcase
Published Wednesday in Jira

Make your Atlassian Cloud products more secure: our NEW admin security guide

Hey admins! I’m Dave, Principal Product Manager here at Atlassian working on our cloud platform and security products. Cloud security is a moving target. As you adopt more products, employees consta...

91 views 0 4
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you