Logging Time - Rolling up to the Epic

Hello, 

 

When my team logs time at the subtask level that information is rolled up to the story. How come the totals at the story level are not rolled up to the parent epic? The estimated and remaining values from the child stories exist on the epic and appear to update but not the logged time. 

 

What is the reasoning behind this? Is this something on the roadmap to change?

2 answers

following as I am interested in the answer to this too.

Out of box JIRA cannot provide you this information.

However as a workaround try this.

  • use search to search for the issues underneath the epic.

epiclink=<name of epic>

  • add Sigma time logged and sigma remaining time to the columns
  • Extract theinformation into an excel
  • Use excel features to sumup the total of time logged  and remaining estimate.

Rahul

 

This seems like a fairly shocking omission, very much a basic project management tool. Do you have an ETA to resolve this issue? Thanks.

Suggest an answer

Log in or Join to answer
Community showcase
Sarah Schuster
Posted Jan 29, 2018 in Jira

What are common themes you've seen across successful & failed Jira Software implementations?

Hey everyone! My name is Sarah Schuster, and I'm a Customer Success Manager in Atlassian specializing in Jira Software Cloud. Over the next few weeks I will be posting discussion topics (8 total) to ...

3,076 views 13 18
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you
Atlassian Team Tour

Join us on the Team Tour

We're bringing product updates and pro tips on teamwork to ten cities around the world.

Save your spot