I'd like to know if it's possible for a Sub-task to automatically heir "Labels" from its parent whe

Swaroop April 30, 2021

Hi Team,

Is It possible

 I'd like to know if it's possible for a Sub-task to automatically heir "Labels" from its parent when [the sub-task is] created.

Please give the step wise.

Thanks

1 answer

2 votes
Bill Sheboy
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
April 30, 2021

Hi @Swaroop 

If you have the Automation for Jira add-on installed, you can do this.  There is a free Lite version and a paid Pro version; both should work.

Please look over these sources to learn how to do this:

Your rule would basically be:

  1. Trigger: issue created
  2. Condition: is a sub-task
  3. Action: edit labels, copying from the parent

 

Best regards,

Bill