Planned for a particular sprint but unable to work on it need to move a set of tickets to other sprint how Do we change dates
Hi @Bhagyamalla ,
If you have planned a set of issues in a sprint and realise during the sprints period that you need to move them to the next sprint you can work from the backlog view mark one or more issues in the active sprint and then drag them down to the backlog (or other sprint if that has been created)
You can also create a filter based on your active sprint and choose bulk change > edit fields > change the sprint field.
best regards