Can I simultaneously have different length sprints in the same JIRA project?

Or do they need to match for all Scrums/Teams? The last related answer is 2 years old (https://answers.atlassian.com/questions/241597)...

We are running 6.3.6 but upgrading this spring to current/JIRA Software. Thanks!

1 answer

We are running JIRA 6.4.11 and sometimes have had sprints of different lengths because a team done goofed and closed a sprint too early (and you can't reopen it, not in our version at least )o:

If you need to calculate department metrics over teams, coordinate builds at the end of sprints and/or have team members helping out other teams, you may run into issues (we did), but nothing in JIRA itself prevents it that I can think of.

Don't think I would recommend it in a single project, however.

Just my $0.02 worth

Suggest an answer

Log in or Sign up to answer
Community showcase
Published Nov 29, 2018 in Jira

How to set up an incident workflow from the VP of Engineering at Sentry

Hey Atlassian community, I help lead engineering at Sentry, an open-source error-tracking and monitoring tool that integrates with Jira. We started using Jira Software Cloud internally last year, a...

1,087 views 0 8
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you