Unable to view Target Start and End Date in issue view.

Is it possible to view the Target start and Target End Date values of an issue set in Jira plan from a Jira board?

1 answer

1 accepted

1 vote
Answer accepted
Pramodh M Community Leader Aug 29, 2022

Hi @Asokan 

You will need to add the fields in screen. The fields will be visible if there is value in the screen.

The fields are from the Advanced Roadmaps and make sure you have field avlues set

Thanks,
Pramodh

Hi Pramod,

Thanks for that. I'm able to see and edit the fields from the issue view now.