Sum of Time Tracking for Issues, Tasks and Subtasks within an Epic

Jenny Davies July 9, 2019

We have Epics for tracking time banks/support and maintenance plans. In my Epic view I can see "Issues in this epic", some are done, but the Time Tracking field is showing "No time logged" despite time being logged to Issues within the Epic. How do I get the Time Tracking field to show me a sum of everything within the Epic, not just subtasks. 

1 answer

0 votes
Lime Trees July 9, 2019

Hi,

you can have a look at our app Status History PRO and its feature which shows hours logged for all issues, tasks and sub-tasks not only for Epic, but also for Story and Task, depending on your needs. More details you can find here.

Regards,

Lime Trees Support Team

Suggest an answer