How to update a table of main issue from subtask

Sadia S Indikar May 23, 2023

How to update a table of main issue from subtask

if the resolution status of the sub task is N/A, then the other columns of the table should populate N/A.

 

 

1 answer

0 votes
Graham Twine
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
May 23, 2023

Hello @Sadia S Indikar 

 

When you say the Sub-task resolution is N/A.

Do you mean it is not set yet or is the resolution updated to N/A?

 

One can use automation, if you have scriptrunner a groovy script  in the workflow or a listener should meet your needs.

Sadia S Indikar May 24, 2023

When the resolution is updated to N/A, I want the other fields of the table of the main issue to be automatically updated to N/A.

Can you please suggest me steps for the same.?

Suggest an answer

Log in or Sign up to answer