How to modify history of SP values for Version Report?

Hi,

We are using the new boards in JIRA and Version Report burn up graph in the Greenhopper boards in version 6.2.2.2.

I accidentally put in 3000 story points instead of 30 into the PBI, I immediately noticed and changed to 30 - however the history now records the huge SP value and the version report has a sharpe spike up for the one minute the story had 3000SP. This has sacaled the whole graph to have a huge amount of whitespace at the top of the graph because of the spike.

Can I get JIRA to forget the PBI ever had the 3000SP value and fix the graph and project history?

Thanks

Stephen

1 answer

1 accepted

0 votes
Answer accepted
Timothy Chin Community Champion Jun 18, 2013

The values come from the issue's change history. So, you would be required to remove the value from the ChangeGroup and the corresponding ChangeItem table.

Thanks for the answer.

Could I just modify the value 3000 to be 31 so as not to delete any data but to limit the impact?

Timothy Chin Community Champion Jun 18, 2013

Of course you can. Also, reindex to make sure that the search picks up these changes.

Suggest an answer

Log in or Sign up to answer
Community showcase
Published Feb 26, 2019 in Jira Software

How to prevent the propagation of unused project schemes, workflows & screens in Jira software

Atlassian ranks project attributes as the third most important factor impacting performance in the category of data. It’s not surprising, since project attributes are precisely the rules used to ma...

602 views 0 7
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you