Exclude some columns from control chart for kanban process

We are trying to use kanban process for our project, but we have a very large backlog. Only part of this backlog should be brought for implementation using kanban process and be counted against the WIP (and used on control chart).

At the same time, we do'nt want to delete all those issues from the system and we would prefer to have a column (or a stack) on a board, from which we could quickly bring in new tasks to work on.

Is it possible to specify which columns are taken into account for all the statistics and WIP calculation?

1 answer

1 accepted

I have missed "Refine..." button on the chart page. It does provide required functionality.

Suggest an answer

Log in or Sign up to answer
How to earn badges on the Atlassian Community

How to earn badges on the Atlassian Community

Badges are a great way to show off community activity, whether you’re a newbie or a Champion.

Learn more
Community showcase
Published May 21, 2018 in Jira Software

How large do you think Jira Software can grow?

Hi Atlassian Community! My name is Shana, and I’m on the Jira Software team. One of the many reasons this Community exists is to connect you to others on similar product journeys or with comparabl...

1,208 views 10 18
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you