I am in jira project "OELZ" and want to assign some epics, but the list also shows me a lot more epics from project "AF", which are done and which I don't want to see here:
according to the post here, this issue should be solved
Unfortunately, with reference to the given ticket, atlassian did not restrict the epics scope to a project but only fine tunes the list better with suggestions and filtering out done issues.
And about the 'done epics', it doesnt refer to the status or resolution. Epics have a special field called 'epic status'. When that value is set to 'done', then the epic is considered as done.
go to the backlog and "Mark as Done" the epics what are in DONE status or configure an automation to "Mark as Done" alone when the epic is transitioned to DONE.
Best regards.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.